Day 1: The Old Loft
Water tanks removed, windows being fitted.

Day 4: Floor Joists in Position
New 200mm by 50mm flooor joists have been fitted as per structural calculations, insulation is laid between joists. Floor board ready to be laid.

Day 6: Dormer Being Built
New dormer is being built to allow for new staircase.

Day 8: Insulation
Insulation is complete and plasterboard is ready to be fitted.

Day 15: Complete on Time
Finished on time. Three weeks from start to finish.